American River Canyon Drive
Awarded by PG&E in January 2025, our team is delivering a comprehensive gas infrastructure replacement spanning American River Canyon Drive in Folsom, extending east on River Ridge Way and west on Oak Canyon Way. The scope includes installation of approximately 2,478 linear feet of 4" gas main, 8,466 linear feet of 2" gas main, 119 gas service replacements, 25 gas service transfers, and deactivation of over 10,500 linear feet of existing 1-1/4", 2", and 4" gas main, utilizing both open trenching and horizontal directional drilling methods.
During the 2025 season, our crews installed 2,531 linear feet of 4" gas main, 8,408 linear feet of 2" gas main, completed 59 gas service replacements and 21 gas service transfers, and deactivated 2,376 linear feet of existing main. The remaining scope is on track for completion in 2026.